wpid-wpid-modot-logo-200x150-200x150.jpgST. JOSEPH, Mo. –Several bridges in northwest Missouri are scheduled for under-bridge inspections over the next few weeks. Crews from the Missouri Department of Transportation may close a single lane on the bridges and ramps listed below as they conduct routine under-bridge inspections. Some of these work zones may be moving operations and motorists are advised to be alert for work zone signs and extra equipment on the roadways around these bridges and ramps.

MoDOT said In-depth under-bridge inspections are part a program of inspection, repair and maintenance of the more than 10,000 bridges across the state. This program ensures the bridges are kept in the best possible condition for as long as possible for all those that travel across Missouri’s roadways.

All work is weather permitting and could be rescheduled.

Week of December 12

Atchison County Route 111 bridge over Mill Creek
Worth County Route 246 bridge over the Platte River

Week of December 19

Linn County U.S. Route 36 bridges over Muddy Creek

Week of January 9

Buchanan County U.S. Route 36 bridges over Route 759
Andrew County U.S. Route 169 bridge over the Platte River
Andrew County Route C bridge over the One Hundred and Two River